On Monday 2nd September, we were granted the building warrant for the site...
- Tuesday: The digger arrived on site. The ground was then levelled and marked out ready for foundations
- Thursday: Foundations were dug, inspected, approved and concrete poured into them
- Tuesday 10th: Steelworks were erected
- Wednesday 11th: Dwarf underground walls built